Don't close this page .. Test is protected .. Answers cannot be changed .. We try now to connect to save and correct your answers.
Connection trial number:
If this message persists for long, please check your internet connection.
This test is monitored
Switching to another webpage or any other program is considered a cheating behavior and your test may be automatically terminated.
Okay
Important Notice
If you moved to the next question, you will not be able to come back to this question again.
Cancel
Move to next question
Project Management Professional | PMP | ادارة المشاريع الاحترافية Quiz 1
Student data
×
Student data
Student name: ***
Student number: ***
Class or section: ***
Test instructions
×
Test instructions
Page direction
×
Change page direction
Right to left
Left to right
Q1
Score: 1
1. 350
2. -75
3. 400
4. -50
Q2
Score: 1
1. promote from within.
2. hire the best.
3. move people into project management because they are good in their technical fields.
4. move people into project management because they have had project management training.
Q3
Score: 1
1. Perform quality control
2. Perform quality assurance
3. Plan Quality Management
4. Variable analysis
Q4
Score: 1
1. the team rank the project risks.
2. the project manager estimate the project.
3. the team schedule the project.
4. management know how other managers will act on the project.
Q5
Score: 1
1. Back charge contracts.
2. Fixed price contracts.
3. Progress payment contracts.
4. Cost plus contracts.
Q6
Score: 1
1. Planning
2. Executing
3. Monitoring and controlling
4. Closing
Q7
Score: 1
1. Temporary
2. Definite beginning and end
3. Interrelated activities
4. Repeats itself every month
Q8
Score: 1
1. Invitation to bid.
2. Request for information.
3. Request for proposal.
4. Request for bid.
Q9
Score: 1
1. Perform Quantitative Risk Analysis and Identify Risks
2. Identify Risks and Control Risks
3. Perform Qualitative Risk Analysis and Control Risks
4. Identify Risks
Q10
Score: 1
1. control tool.
2. scheduling method.
3. planning tool.
4. rule of thumb.
Q11
Score: 1
1. Functional
2. Matrix
3. Expediter
4. Coordinator
Q12
Score: 1
1. Makes it easier to find vendors
2. Increases company expertise in contracting
3. Gives more loyalty to the project
4. Allows a contracts person to work on a single project
Q13
Score: 1
1. Physiological satisfaction
2. Attainment of survival
3. Esteem
4. Self-actualization
Q14
Score: 1
1. create a project scope statement.
2. confirm that all the stakeholders have contributed to the scope.
3. analyze project risk.
4. begin work on a project management plan.
Q15
Score: 1
1. Cost plus percentage of cost as an award fee
2. Cost plus fixed fee
3. Cost plus incentive fee
4. Firm fixed price
Q16
Score: 1
1. A clear contract statement of work
2. Requirements as to which subcontractors can be used
3. Incentives
4. A force majeure clause
Q17
Score: 1
1. Understand the experience of the sponsor on similar projects.
2. Create an activity list.
3. Make sure the project scope is defined.
4. Complete risk management and issue the responsibility assignment matrix.
Q18
Score: 1
1. Project engineer
2. Project manager
3. Quality manager
4. Team member
Q19
Score: 1
1. Work breakdown structure.
2. Budget baseline.
3. Project charter.
4. Project plan.
Q20
Score: 1
1. Who will be a member of the change control board
2. Spending more time on configuration management
3. Getting a single project sponsor
4. Determining the reporting structure