رقم السؤال: 1           درجة السؤال: 1
 1. The number of days the project will be late divided by the project duration
 2. The percent of time a given activity will be on the critical path
 3. The percent of time an activity will be late
 4. The sum of the duration of the critical path activities divided by the project expected value for duration.
رقم السؤال: 2           درجة السؤال: 1
 1. Earned value (EV)
 2. Planned value (PV)
 3. Actual cost (AC',
 4. Cost variance (CV)
رقم السؤال: 3           درجة السؤال: 1
 1. $100,000
 2. $114,500
 3. $117,000
 4. $119,500
رقم السؤال: 4           درجة السؤال: 1
 1. Validating scope
 2. Controlling the schedule
 3. Performing Change Control
 4. Manage Stakeholder Engagement
رقم السؤال: 5           درجة السؤال: 1
 1. Reduce the time needed to do the project.
 2. Increase the total time necessary to do all the tasks.
 3. Reduce the overutilization of resources.
 4. Reduce resources to the lowest skill that is possible.
رقم السؤال: 6           درجة السؤال: 1
 1. withdrawing.
 2. directing.
 3. organizing.
 4. controlling.
رقم السؤال: 7           درجة السؤال: 1
 1. 1
 2. 3
 3. 0.85
 4. 2
رقم السؤال: 8           درجة السؤال: 1
 1. 0.75
 2. 1.50
 3. 0.25
 4. 1.15
رقم السؤال: 9           درجة السؤال: 1
 1. Alert the project sponsor of potential impacts to cost, scope or schedule.
 2. Qualify the risk.
 3. Mitigate this risk by developing a risk response plan.
 4. Develop a workaround.
رقم السؤال: 10           درجة السؤال: 1
 1. The project plan.
 2. The project goals and objectives.
 3. The project charter.
 4. The project definition.
رقم السؤال: 11           درجة السؤال: 1
 1. The project is incomplete because the project needs to be re-planned.
 2. The project is incomplete until all the activities required for closing a project are completed.
 3. The project is complete because the customer has accepted the deliverables.
 4. The project is complete because the project has reached the due date.
رقم السؤال: 12           درجة السؤال: 1
 1. confronting.
 2. compromise.
 3. smoothing.
 4. forcing.
رقم السؤال: 13           درجة السؤال: 1
 1. Projectized organization.
 2. Strong matrix organization.
 3. Weak matrix organization.
 4. Balanced matrix.
رقم السؤال: 14           درجة السؤال: 1
 1. Perform a design of experiments.
 2. Adjust the chart to reflect the new mean.
 3. Find an assignable cause.
 4. Nothing. This is the rule of seven and can be ignored.
رقم السؤال: 15           درجة السؤال: 1
 1. Check risk status.
 2. Check cost performance.
 3. Check progress reports.
 4. Tell the team your objectives.
رقم السؤال: 16           درجة السؤال: 1
 1. verbal
 2. written
 3. formal
 4. nonverbal
رقم السؤال: 17           درجة السؤال: 1
 1. PERT analysis
 2. GERT analysis
 3. Monte Carlo analysis
 4. Critical path method
رقم السؤال: 18           درجة السؤال: 1
 1. Project Appraisal.
 2. Monitoring and Controlling Process.
 3. Planning Process.
 4. Progressive Elaboration.
رقم السؤال: 19           درجة السؤال: 1
 1. Initiating
 2. Executing
 3. Planning
 4. Closeout
رقم السؤال: 20           درجة السؤال: 1
 1. Project management plan
 2. Communications management plan
 3. Configuration management plan
 4. Quality management plan


   